The main construction of the LERCO research centre is completed
In less than a year, builders have completed the rough construction phase, and the project has now progressed to the interior. Work is currently underway on interior plumbing, HVAC systems, electrical wiring, partition walls, and drywall installation. The building's character is gradually taking shape as workers install window frames and prepare the structure for winter, ensuring that construction can continue uninterrupted during the colder months.
Founding an object
The next step of construction has begun for LERCO. After the excavation of the main construction pit, work on the deep foundation of the building is now underway. The drilling and concreting of approximately one hundred large-diameter piles with lengths of almost twenty metres is underway.